LINKS
ARCHIVE
You are not logged in. Log in
28 August 2005
Another Injury
Well, it wasn't jobsite related, unlike my father-in-law's minor injury last weekend which resulted in six stitches at his knee.

I simply tripped in our own driveway at home, and now... I have a broken foot. Six to eight weeks in a cast. I probably won't be able to walk inside the house to see the rough framing myself. What an inconvenience... argh!

Posted by julietiu at 14:30 CDT
Post Comment | Permalink
27 August 2005
No Problem...
Here are some pictures from the basement slab pour. We officially start carpentry on Monday. The open-web trusses are on site now, and the loose material (studs, plates, etc.) are being delivered today - now. Ralf and Tom our carpentry foremen seem to be unphased by the unconventional framing scheme of our house. Famous last words "No Problem..." Domingo has been drafting several connection details and double, triple checking dimensions. He met with Ralf last Wednesday, started pointing out some things, and from what I understand, all he had to say was "No problem..." Is this reassuring? I'm a little nervous, to say the least.

And, I know for a fact the carpenters haven't even looked at the drawings in relation to the lumber material list. Again, I don't find this terribly reassuring. In jest, they said, "We'll just see what they (lumber supplier) bring us, and we'll work with what we have," though, I don't know if they were really joking.

I was really hoping they were going to review the material list. The last thing I want to hear is, "Julie, we're short on the lumber material..." and then have them stop working. If anything, they should just truck themselves to the local Home Depot and buy what they're short.

Well, Monday should prove to be interesting. I wonder what sort of phone calls I'll be receiving. In the meantime, we're trying to figure out flooring finishes for finished floor height and plumbing fixtures (toilets, tubs, etc.). You'd be surprised how much all your selections affect the construction in the "rough" stage. More thoughts to come.

Posted by julietiu at 07:51 CDT
Post Comment | Permalink
20 August 2005
Things You Might Overhear at the Tiu Home
Domingo: We're not building a watch (Swiss watch...).
Eastman: I don't KNOW... I'm just asking.
Julie: No...no...no...
Abby: Stop yelling.
(I guess Mom has her two cents in, but it's usually when I'm at work.)

Everyone (including tradespeople): You can make it a wine cellar! (In reference to the open space underneath the front porch due to the mistake in excavation.)

The basement slab was poured yesterday, and Project Engineer Eastman was quite interested in the operations. Here is his log from yesterday.

"Basement poured and looks great! We put up a fence in front of the porch hole and sprayed the front of the garage too. Pops dropped the paint cap (flipped out of his hands when he was taking it off actually) and it fell into the basement. It was before they were doing final smooth out though, so it's all good. BTW, they used cieling tile dividers as control joints, and they put them under the slab so the slab is actually all smooth. No visible control joints."

remote Posted by julietiu at 09:47 CDT
Updated: 20 August 2005 09:48 CDT
Post Comment | View Comments (1) | Permalink
18 August 2005
Rain Delay
Ah... no basement slab pour today due to the rain. Perhaps tomorrow.


remote Posted by julietiu at 12:20 CDT
Post Comment | Permalink
15 August 2005
Almost Out of the Ground
The foundation walls were poured a week ago today, and from many onlookers we've received many compliments. Dampproofing is all set also, and the backfill inspection went without a hitch. Amazingly enough, the spot survey showed that the foundation was right on the money; within .01 feet of where it should be.

Husband and father-in-law are doing one heck of a superintending job. Will definitely be more difficult once school starts up again and we lose our "project engineer".

These are pictures of the foundation walls as it stands today. More pictures are on our online albums - by invite only.

Posted by julietiu at 20:29 CDT
Post Comment | Permalink
4 August 2005
An Impressive Operation
The foundation work has finally begun this week. Tomorrow they pour the foundation walls. Our concrete subcontractor has been great to deal with thus far, and we're looking forward to seeing the basement walls stand on their own. Had a bit of a logistics problem when the conveyor was having a difficult time getting under the power lines.

Floor trusses are in production and should be available in a few weeks. Underground plumbing and electrical service will start as soon as we get get the basement walls dampproofed and backfilled.

It's been tiring, but exciting for the field superintendent and project engineer (my father-in-law and husband, respectively). Wish I could be on site a little more often.

Will post pictures soon.

Posted by julietiu at 20:28 CDT
Post Comment | Permalink
29 July 2005
Dirty Work
Excavation ended this past Wednesday. Were supposed to start forming the footings this morning in anticipation of an afternoon (concrete) pour. Well... the foundation hole was dug a little too close, too tight. When I got the call, it didn't even phase me. My father-in-law/site superintendent/architect wasn't too surprised either. On the other hand, my husband was pretty frustrated.

The excavator will just come back tomorrow, and we'll try to pour again on Tuesday. I keep thinking, we just have to get out of the ground and we'll be up and running! (Right?) Some friends have commented that things will just get worse as the days go by; that's probably true.

Well, onward and upward... we'll meet with a stair contractor tomorrow morning. See what other cans of worms we can open up!

remote Posted by julietiu at 17:18 CDT
Post Comment | Permalink
21 July 2005
What a Start
Excavation started today, and a live gas line was hit. Nice way to start. Dumb me, I should've thought about calling the utility locators again.

NICOR is out there now. Of course, in a non-emergency case, it'd take probably two to three weeks to get the gas utilities to the site. So, maybe there's a silver lining after all.


remote Posted by julietiu at 10:46 CDT
Updated: 21 July 2005 10:48 CDT
Post Comment | Permalink
17 July 2005
FINALLY
Just received the permit on Friday - exactly one year from the date we went to the Appearance Commission and received our approval. I'd like to think we took eight months to work out design and four months to get paperwork and contractors in line. We haven't even figured out all the interior selections yet. Argh.

Excavation should begin on Wednesday. It hasn't rained in what feels like all summer, and wouldn't you know it... the weather people are forecasting rain this week. We'll keep our fingers crossed.

Now the madness REALLY begins!

Posted by julietiu at 20:50 CDT
Post Comment | Permalink
26 June 2005
Coordination... coordination...
It's been several days without rain here, and there has been no construction yet. Sort of a waste of good weather, though the temps have been in the high 90s. Guess the crews could've been working early in the A.M.

We don't have permit yet, only because we don't have everyone contracted. Argh. You'd think the City could let us have a "foundation only" permit. Called the floor joist suppliers and they won't be able to deliver anything (realistically) for 4-5 weeks. Have to get them on board too. Kitchen cabinets has been quite a trip as well.

Lastly, our interior consultant has just notified us that she's moving to Atlanta in two weeks (less than that at the time of this post). We've barely begun working with her, which is a good thing, I suppose. However, I was really looking forward to having her help.

Maybe it would've been easier hiring a GC?

Posted by julietiu at 17:45 CDT
Post Comment | View Comments (1) | Permalink

Newer | Latest | Older