Deliveries, deliveries
Shingles are on, and the windows arrived at the distribution facility yesterday! Hooray! The brick arrived at the site moments ago...two weeks early, but not so good. There's sewer work being done in the front yard, and there's nowhere for the brick to sit.
Hectic, hectic...
UPDATE from the FIELD:
Masonry : Bricks were delivered this morning, big surprise to everybody. (Mason) claimed he never told Illinois Brick to deliver today. when they arrived, plummer had already dug out the driveway for the sewer work. (Supplier) refuses to take the bricks back to their yard. at the end we were able to take out the orange fence between the driveway and the tree, they then use a folklift to get the bricks in. the bricks are now sit on the east side of the driveway.
Plumbing : they will finish the outside sewer work today in front, hole to be covered. Inspector came, approved the connection .
Tom wants to start plumbing rough-in next Monday. we need to get him all fixtures cuts and kitchen sink cabinet layout.
They started work this morning at 6:30am, the neighbor at the corner came by and complained.
Windows : I am still waitng for the exact delivery time, carpenter want them on next Monday morning.
Masonry : (Mason) will start also on Monday to put down the flashings, I gave him a check for stones and other materials, he will give as a detailed receipt, his masons will start work in Tuesday or Wednesday. He will use a regular scaldfolding which is 6'-0" wide. we need to talk to our neighbor for permission, they will put down protective cover on the ground. the stone will be deliver on Tuesday afternoon.
Posted by julietiu
at 08:46 CDT
Updated: 28 September 2005 12:39 CDT